Confidently Practice Online with Free CCM Exam Cram

Practice your Certified Contract Manager certification test with free CCM exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real CCM exam dumps, verified questions, and expert-designed free online practice tests. Moreover our FIDIC CCM exam cram backed by our confidence-boosting refund guarantee.

Exam Code: CCM
Exam Questions: 101
Certified Contract Manager
Updated: 26 Nov, 2025
Viewing Page : 1 - 11
Practicing : 1 - 5 of 101 Questions
Question 1

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme? Choose all of the correct answers (multiple possibilities) 

Options :
Answer: A,B

Question 2

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?

Options :
Answer: D

Question 3

You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months. The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit. 1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022. The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date. What is the correct Commencement Date?

Options :
Answer: D

Question 4

The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract backto-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions: "Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted." What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?

Options :
Answer: C

Question 5

Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?

Options :
Answer: A

Viewing Page : 1 - 11
Practicing : 1 - 5 of 101 Questions

© Copyrights FreeExamCram 2025. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeExamCram). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeExamCram.