Practice your Cognitive Project Management in AI CPMAI v7 certification test with free CPMAI_v7 exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real CPMAI_v7 exam dumps, verified questions, and expert-designed free online practice tests. Moreover our PMI CPMAI_v7 exam cram backed by our confidence-boosting refund guarantee.

Exam Code: CPMAI_v7
Exam Questions: 102
Cognitive Project Management in AI CPMAI v7
Updated: 05 Jan, 2026
Viewing Page : 1 - 11
Practicing : 1 - 5 of 102 Questions
Question 1

You recently completed an image recognition project at your company that was focused on identifying different types of cars. You have now been assigned a new image recognition project that is focused on identifying different types of animals. You know you can shortcut model development by using a specific technique. What is this technique called? 

Options :
Answer: C

Question 2

Your team has built a new robot that roams the halls at your organization and helps with various things such as small deliveries. However, you notice that many employees are opting not to use the robot. When you ask them why they tell you that the robot looks "creepy" and they would rather not interact with it. What's going on here?

Options :
Answer: B

Question 3

You're working on a project and are working with personally identifiable information (PII). What's the best approach to take when it comes to collecting and using this data?  

Options :
Answer: D

Question 4

You're working on a project and are working with personally identifiable information (PII). What's the best approach to take when it comes to collecting and using this data?  

Options :
Answer: D

Question 5

A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months. What's wrong with this timeframe?

Options :
Answer: D