Practice your Certified Tester Advanced Level Test Management (CTAL-TM) v3.0 certification test with free CTAL-TM exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real CTAL-TM exam dumps, verified questions, and expert-designed free online practice tests. Moreover our ISTQB CTAL-TM exam cram backed by our confidence-boosting refund guarantee.
Assuming that 'In progress' means that somebody is working on a fix and that 'Resolved' means that the fix passed the confirmation test; which option provides a defect workflow that flows in a sensible way from an initial state to a terminal state?
SCENARIO
‘Safe as Houses’ is a company that specializes in home security software, including alarm systems,
surveillance cameras and other forms of deterrence.
It is currently developing the software for a device which simulates an active television, producing sound and
light images that suggest someone is home watching the television. ‘Safe as Houses’ recently won a lucrative
contract to supply the software to ‘Smart Alarms’, who will be manufacturing the hardware devices. Sound will
be created using actual television and film archives, licensed through a third-party supplier, ‘Silver Sound Ltd’. A
user interface will be developed in house to allow the customer to choose sound tracks.
The software will be delivered as a program of work, consisting of three projects. Project 1 will develop the
software for the light images, Project 2 will develop the sound system and Project 3 will integrate the two using
hardware prototypes supplied from ‘Smart Alarms’. The program will conclude with ‘Smart Alarms’ performing
User Acceptance testing in usability labs.
The ‘Safe as Houses’ test team has experience in testing alarm and surveillance systems but lacks experience
in testing light imagery software. The organizational test policy includes the following objectives:
1. Exploratory testing should be used to augment more formal, structured testing within constraints of time and
budget
2. Test automation tools should be purchased and employed to maximize the breadth and efficiency of
regression testing
The Program risk register currently includes the following risks:

Refer to SCENARIO. It has been agreed that the following test planning documents will be produced:
• A single overarching document outlining the general testing methodology for the whole program of work
• A subordinate test plan for each of the three projects
• A separate test plan for performance testing within each project
Which one of the following options BEST describes the type of test management document that will meet the
program requirements?

Within the projects, a master test plan and phase test plan will be used. Following is a list