Practice your ISTQB Certified Tester Advanced Level - Test Management (Syllabus V3.0, worldwide)(Non Native) certification test with free CTAL-TM_V3_NN exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real CTAL-TM_V3_NN exam dumps, verified questions, and expert-designed free online practice tests. Moreover our iSQI CTAL-TM_V3_NN exam cram backed by our confidence-boosting refund guarantee.

Exam Code: CTAL-TM_V3_NN
Exam Questions: 463
ISTQB Certified Tester Advanced Level - Test Management (Syllabus V3.0, worldwide)(Non Native)
Updated: 22 May, 2026
Viewing Page : 1 - 47
Practicing : 1 - 5 of 463 Questions
Question 1

You are about to release a test progress report to a senior manager, who is not a test
specialist. Which of the following topics should NOT be included in the test progress
report? 1 credit

Options :
Answer: D

Question 2

You are a Test Manager working on an Agile project that is in the 2nd week of test execution for System Test

Sprint 1. The number of failures has exceeded expectations as shown in the following diagram:

Given only the information provided in this question, which of the following action plans COULD prevent a
similar situation occurring again in the next sprint?
a) More testing resource to be provided during system testing
b) More development resource to be provided during system testing
c) Tighten the entry criteria into system testing
d) Improve the reviews of requirement specifications
e) Allocate more time for testing
f) Developers to test more prior to handover
g) Implement better estimation of the failures to be found

Options :
Answer: D

Question 3

You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks and determining the likelihood and impact of those risks. You have been testing for three months and have been able to mitigate 75% of the high risk items. You have two weeks left in testing and you now do not expect to be able to complete all the items on the high-risk mitigation list, never mind any from the medium or low-risk lists. What is the most effective action you should take?

Options :
Answer: B

Question 4

Topic 11, Scenario 11 "Incident Management"
The following is the current incident handling process in used at the company.
Step 1: Incident is documented in the incident Tile with the following information:
- Software module or area where the fault occurred
- Who has reported the fault
- Hardware configuration used for the test that found the fault
- The sequential incident number (1 greater than the last one recorded)
Step 2: Developer assigned to fix the fault
Step 3: Developer fixes the fault
Step 4: Developer signs off the incident as closed, and it is then removed from the incident
file

As a result of the RAD based development approach, the test manager has decided to
change the risk mitigation approach. Which test technique might be most appropriate to
use? 2 credits

Options :
Answer: D

Question 5

2.1 You are overseeing a large-scale software development project for a financial institution. The project has tight deadlines, and you need to ensure that the testing process is efficient and meets high-quality standards. Your goal is to use metrics to optimize the testing process and ensure all test objectives are met. Considering the need for efficiency and high quality in the financial sector, which of the following metrics would best help you assess the capability of the testing process and its alignment with the project's quality goals?

Options :
Answer: C