Practice your ISTQB Certified Tester Advanced Level - Test Management (Syllabus V3.0, worldwide)(Non Native) certification test with free CTAL-TM_V3_NN exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real CTAL-TM_V3_NN exam dumps, verified questions, and expert-designed free online practice tests. Moreover our iSQI CTAL-TM_V3_NN exam cram backed by our confidence-boosting refund guarantee.

Exam Code: CTAL-TM_V3_NN
Exam Questions: 463
ISTQB Certified Tester Advanced Level - Test Management (Syllabus V3.0, worldwide)(Non Native)
Updated: 16 Apr, 2026
Viewing Page : 1 - 47
Practicing : 1 - 5 of 463 Questions
Question 1

3.1.5 What skill is crucial during the "Storming" phase of the Tuckman model of small group development? 

Options :
Answer: B

Question 2

You are a Test Manager working on an Agile project that is in the 2nd week of test execution for System Test

Sprint 1. The number of failures has exceeded expectations as shown in the following diagram:

Given only the information provided in this question, which of the following action plans COULD prevent a
similar situation occurring again in the next sprint?
a) More testing resource to be provided during system testing
b) More development resource to be provided during system testing
c) Tighten the entry criteria into system testing
d) Improve the reviews of requirement specifications
e) Allocate more time for testing
f) Developers to test more prior to handover
g) Implement better estimation of the failures to be found

Options :
Answer: D

Question 3

Topic 8, Scenario 8, V2 "Test Proems Improvement'
You have raised the issue that improving the testing process is also dependent on the
status of the software development process.

Identify THREE items that would be part of the work-breakdown structure showing the key
testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)

Options :
Answer: A,B,D

Question 4

Which of the following is a valid drawback of independent testing? 1 credit

Options :
Answer: B

Question 5

Topic 10, Scenario 10, V3 "Online Application"
The cancellation of a current major development project has released resources. The
development manager has decided to respond to his own request to tender and has
proposed an in-house development with the use of a Rapid Application Development
(RAO) approach.

Which THREE activities would be valid steps during the development of the test strategy?2
credits (2 out of 3 correct 1 credit)

Options :
Answer: A,C,D