Practice your ISTQB Agile Tester Foundation certification test with free CTFL-AT exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real CTFL-AT exam dumps, verified questions, and expert-designed free online practice tests. Moreover our ISTQB CTFL-AT exam cram backed by our confidence-boosting refund guarantee.

Exam Code: CTFL-AT
Exam Questions: 317
ISTQB Agile Tester Foundation
Updated: 21 May, 2026
Viewing Page : 1 - 32
Practicing : 1 - 5 of 317 Questions
Question 1

Which TWO of the following statements are true on agile projects?
A. Testers should work closely with developers while retaining an objective outlook.
B. Test managers do not exist in organizations doing agile development.
C. There is no difference between what testers and developers do on agile projects.
D. Developers should rely on testers to create the automated regression tests.
E. A selection of users may perform beta testing on the product after the completion of a series of iterations.

Options :
Answer: C

Question 2

Which of the following is NOT a part of twelve principles of Agile Manifesto?
i. Simplicity - the art of maximizing the amount of work not done - is essential.
ii. the most efficient and effective method of communication is through face-to-face conversation.
iii. Making quality everyone's responsibility.
iv. Trust motivated individuals and give them the support and environment; build projects around them.
v. Promote consistent project momentum

Options :
Answer: D

Question 3

Which of the following is a risk that continuous integration introduces? 

Options :
Answer: B

Question 4

An Agile team uses a burndown chart and a task board to track progress within each iteration. In the burndown chart, the x-axis represents the days of iteration, while the y-axis represents the story points. The task board uses columns: "To Do", "Ongoing", "Done". A user story for the current iteration has 20 story points and 4 tasks (T1, T2, T3, T4). At the end of Day 5, all are in "Ongoing". At the end of Day 6, T1 and T2 move to "Done", while T3 and T4 remain "Ongoing". Which of the following statements would you expect most likely to be true at the end of Day 6?

Options :
Answer: C

Question 5

Which of the following statements is FALSE regarding early and frequent feedback? 

Options :
Answer: A