Confidently Practice Online with Free L6M5 Exam Cram

Practice your ELECTIVE Strategic Programme Leadership certification test with free L6M5 exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real L6M5 exam dumps, verified questions, and expert-designed free online practice tests. Moreover our CIPS L6M5 exam cram backed by our confidence-boosting refund guarantee.

Exam Code: L6M5
Exam Questions: 122
ELECTIVE Strategic Programme Leadership
Updated: 26 Nov, 2025
Viewing Page : 1 - 13
Practicing : 1 - 5 of 122 Questions
Question 1

KCJ Ltd is a public sector organisation which is looking to run 5 projects over the next financial year. Below are details of each project:
Project 1: The budget estimate of this project is calculated using an algorithm. The project lead is the founder of the organisation.
Project 2: The project lead is the Head of Research and Development, who has a PHD in Data Science. He has taken costing and budget information from similar projects conducted previously to decide on a budget for Project 2.
Project 3: The project is being led by a key stakeholder and involves creating a Bill of Materials. Costs will be worked out for each item required to complete the project and totalled together.
Project 4: The Project Leader has worked out the base cost, most likely cost and worst-case scenario for the project. His power comes from his ability to pull the plug on this project at any time.
Project 5: This project is being led by a well-liked member of the Board of Directors. He has selected a team who he gets on well with and has decided the budget based on his own research.
For each project, select the cost estimation method used and the source of power of the Project Leader. Complete the table below, some answers may be used twice: bottom up, 3-point estimate, parametric, analogous, expert judgement, top-down, positional (x2), personal (x2), expert, negative
Which of the following will you put into box 4?
2022-06-01-13-18-51-752844ec27d32eb2a639c2073491ee53

Options :
Answer: B

Question 2

XYZ is a large construction organisation which is currently running five different projects. Below are details of each project including the type of contract and pricing mechanism used.
Project 1: This project is to build an apartment block and the company has responsibility for designing and constructing the building. Upon completion, ownership will pass to the client. Management have decided the pricing based on past experience of similar projects.
Project 2: The company will provide the facilities management to the building for 6 years following the completion of the construction work. Due to volatility in the industry, the budget is changing continuously over the years.
Project 3: XYZ has been involved in the project since an early stage, but does not hold the design risk for the construction of the building. The budget starts afresh at the beginning of each new accounting period.
Project 4: XYZ is responsible for the design and build of certain aspects of the construction. However, the client has also employed another company for other aspects. The client will take ownership from all companies involved upon completion. XYZ is paid when milestones are completed during the building phase.
Project 5: This is the construction of a new toll bridge which will be operated by XYZ for the first 6 years post construction. Pricing is based on the costs of raw materials and labour and a profit is added on top of this.
Complete the table below by listing the type of contract and pricing mechanism being used for each project; design and operate, design build operate and ownership, public private partnership, full turnkey, partial turnkey, management contracting, bottom up, top down, rolling, fixed fee, zero, activity.
Which of the following will you put into box 10?

Options :
Answer: A

Question 3

Giant Construction Company is working on 5 large scale projects. Below are details of each project.
Project 1: Giant is working closely with the client to construct a hospital. The client has provided an estimate of what they think the construction will cost, and any savings will be shared between the parties. This form of contract is popular in the public sector and is being used due to its flexibility.
Project 2: This suite of contracts is known collectively as ‘the rainbow suite’ and is very rigid, not allowing for changes later down the line. The price of the construction was set on the date the contract was signed.
Project 3: This project is for the construction of wind turbines and is an international project. The pricing mechanism accounts for the cost of construction of each individual turbine.
Project 4: This is the most popular form of contract used in the construction industry and uses a Contract Administrator role who is responsible for the timely flow of information to all parties. The scope of the project was not clearly defined at the onset, so Giant is working with the client by sharing their costs incurred plus a small profit margin.
Project 5: This project is for the provision of ICT services and software provision. Giant is paid when certain milestones are met in the implementation of the project.
For each project, select the type of contract and pricing mechanism being used. Complete the table below by listing the type of contract and pricing mechanism being used for each project; CIPS, FIDIC, IMechE, JCT, Joint Venture Contract, NEC, Bill of Quantities, Cost Reimbursable, Cost plus award fee, Fixed Lump Sum, Activity Based Pricing, Target Costing.
Which of the following will you put into box 4?
2022-05-29-11-22-44-c059dc7bcc71482152bf6f13382bf03d

Options :
Answer: D

Question 4

Which of the following processes for managing change is the most passive?

Options :
Answer: D

Question 5

What is the purpose of Cybernetic Control within Project Management?

Options :
Answer: B

Viewing Page : 1 - 13
Practicing : 1 - 5 of 122 Questions

© Copyrights FreeExamCram 2025. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeExamCram). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeExamCram.