Practice your MSP Practitioner Exam (5thEdition) certification test with free MSP-Practitioner exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real MSP-Practitioner exam dumps, verified questions, and expert-designed free online practice tests. Moreover our MSP MSP-Practitioner exam cram backed by our confidence-boosting refund guarantee.

Exam Code: MSP-Practitioner
Exam Questions: 142
MSP Practitioner Exam (5thEdition)
Updated: 15 Apr, 2026
Viewing Page : 1 - 15
Practicing : 1 - 5 of 142 Questions
Question 1

In the programme brief three options were considered:
(1) Keep PCSafe and TechStore as two separate companies
(2) Carry out the merger
(3) Keep the companies separate but with close collaboration
The programme manager is now developing the business case in the 'design the outcomes' process and is reconsidering the options provided, and any new ones that have become apparent as more information is gathered.
Which theme is being applied by the programme manager?

Options :
Answer: D

Question 2

A design workshop was held and the following point was agreed.
In which key document (A-F) should they be recorded as part of the ‘design’ theme?
Choose only ONE document for each item of information. Each document can be used once, more than once, or not at all.
The increase in registered patents will be measured by recording how many have been submitted on a quarterly
and annual basis compared to pre-merger statistics. This will begin once the two R&D teams have been fully
integrated.

Options :
Answer: B

Question 3

The programme manager has asked the Research Manager to present to the programme board.
The presentation will identify what skills will be required to operate the new joint Research and Development function, once the new ways of working have been established.
Is this an appropriate application of the ‘deploy diverse skills’ principle, and why?

Options :
Answer: A

Question 4

The programme is currently in Tranche 2. The COO has been appointed as the SRO and the IT Manager is the programme manager. Due to the SRO’s lack of IT knowledge, the programme manager has found that it is easier to omit reporting about the IT issues as it often worried the SRO, who then created friction with the Process Alignment Project team.
Is this an appropriate application of the 'decisions' theme, and why?

Options :
Answer: D

Question 5

The Sales Channel and Processes Project is due to deliver the new sales processes within the next week. The programme manager and the BCM have been reviewing the new and revised sales processes with the Sales Manager to make sure that they meet the specified needs of the business before they are implemented.
In which activity of the 'deliver the capabilities' process should this review be carried out?

Options :
Answer: D