Confidently Practice Online with Free PMI-CP Exam Cram

Practice your Construction Professional in Built Environment Projects certification test with free PMI-CP exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real PMI-CP exam dumps, verified questions, and expert-designed free online practice tests. Moreover our PMI PMI-CP exam cram backed by our confidence-boosting refund guarantee.

Exam Code: PMI-CP
Exam Questions: 177
Construction Professional in Built Environment Projects
Updated: 26 Nov, 2025
Viewing Page : 1 - 18
Practicing : 1 - 5 of 177 Questions
Question 1

A construction professional is leading a major road construction project to ease traffic congestion in a metropolitan area. During project execution, the contractor, bound by contract to provide regular status reports and participate in progress evaluation meetings, abruptly ceased these obligations, claiming that these activities are excessively time-consuming. The project is at a critical phase with tight deadlines and high stakeholder expectations.

What should the construction professional do first?

Options :
Answer: B

Question 2

During the risk identification phase, the construction professional and their team identified more than 100 risks. The construction professional believes that developing a mitigation plan for each of these risks will take a lot of time, whereas not all of the identified risks are important enough to justify such a measure.

What should the construction professional do next?

Options :
Answer: D

Question 3

During the commissioning and startup of a built environment project, two interface stakeholders disagree about their involvement in a recent work incident, accusing each other of dodging responsibility. To avoid such an issue in the future, the construction professional decides to include a RACI matrix in the Interface Agreement (IA). RACI is an acronym for:

Options :
Answer: D

Question 4

A senior construction professional works on a nuclear power plant which will be planned and executed using the Advanced work packaging (AWP) approach. After the definition of construction work areas (CWAs), the construction professional moved on to the preparation for the workface planning phase. One of the project planning team wondered about the relationship between the Engineering Work Packages (EWP), the Construction Work Packages (CWP), and the Installation Work Packages (IWP).

What should the construction professional’s answer be? (Select two)

Options :
Answer: A,D

Question 5

A construction professional is leading the construction of a new hospital. The project is halfway through its scheduled time frame. The construction professional monitors the scope along with other project constraints, and thinks that, overall, the project seems to be on track. However, some key stakeholders are concerned about potential cost overruns.

What can the construction professional do to address the stakeholders' concerns?

Options :
Answer: B

Viewing Page : 1 - 18
Practicing : 1 - 5 of 177 Questions

© Copyrights FreeExamCram 2025. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeExamCram). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeExamCram.