Practice your PMI Scheduling Professional certification test with free PMI-SP exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real PMI-SP exam dumps, verified questions, and expert-designed free online practice tests. Moreover our PMI PMI-SP exam cram backed by our confidence-boosting refund guarantee.
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?
Mark is the project manager of the NHQ Project. Mark wants to create a salience model as part of his communications planning and scheduling. What does a salience model do for a project?
Holly is the project manager for her organization. Her current project is running late and her project customer has asked Holly to find a method to apply corrective actions to the project schedule. Holly is exploring the concept of crashing the project. Which of the following statements is true about crashing the activities in Holly's project?
You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?
If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?