Practice your Project Management Professional (PMBOK 7th Version) certification test with free PMP exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real PMP exam dumps, verified questions, and expert-designed free online practice tests. Moreover our PMI PMP exam cram backed by our confidence-boosting refund guarantee.

Exam Code: PMP
Exam Questions: 2201
Project Management Professional (PMBOK 7th Version)
Updated: 12 Jun, 2026
Viewing Page : 1 - 221
Practicing : 1 - 5 of 2201 Questions
Question 1

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points. What should the project manager ask the team to do next?

Options :
Answer: D

Question 2

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid What should the project manager do?

Options :
Answer: B

Question 3

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement What should the project manager do next? 

Options :
Answer: C

Question 4

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project. What should the project manager do to address this issue?

Options :
Answer: D

Question 5

While reviewing a project with high-level executives, the project manager realizes that the conversation always deviates to other topics instead of the project itself. What two actions should the project manager take? (Choose 2) 

Options :
Answer: C,D

Viewing Page : 1 - 221
Practicing : 1 - 5 of 2201 Questions