Practice your PRINCE2 Practitioner certification test with free PRINCE2-Practitioner exam cram and take control of your certification preparation. At FreeExamCram, you can practice online for free using real PRINCE2-Practitioner exam dumps, verified questions, and expert-designed free online practice tests. Moreover our PRINCE2 PRINCE2-Practitioner exam cram backed by our confidence-boosting refund guarantee.

Exam Code: PRINCE2-Practitioner
Exam Questions: 375
PRINCE2 Practitioner
Updated: 14 Apr, 2026
Viewing Page : 1 - 38
Practicing : 1 - 5 of 375 Questions
Question 1

Product based planning focuses on which of the following:
1. Creating product descriptions
2. Identifying activities
3. Creating a Product hierarchy
4. Creating a Product sequence

Options :
Answer: A

Question 2

The 'e-learning course' is being delivered by an external consultancy. The testing of the e-learning has been completed by ABC Company’s testers and some faults have been found that still need to be fixed. The team manager for the 'e-learning course' work package believes the faults can be fixed within existing work package tolerances and has raised a request for change with the project manager. Is this an appropriate action, and why?

Options :
Answer: C

Question 3

The delivery of the pilot courses has been split into two separate products: ‘planned pilot courses’ and ‘delivered pilot courses’. ‘Planned pilot courses’ will be produced during stage 3, and the ‘delivered pilot courses’ will take place during stage 4. This will allow the project board to approve the plan for the pilot courses before the resources are committed to delivering the pilot courses. Why is this an appropriate application of the plans theme to control the project? 

Options :
Answer: D

Question 4

The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost £900. The stage 2 cost tolerance of +£1,000 has not been used. The change budget of £500 has not been used. Which option describes how this change should be funded?

Options :
Answer: D

Question 5

ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project. Is this an appropriate application of the ‘tailor to suit the project’ principle, and why? 

Options :
Answer: B

Viewing Page : 1 - 38
Practicing : 1 - 5 of 375 Questions

© Copyrights FreeExamCram 2026. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeExamCram). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeExamCram.